unchanged SCN: Significant Change Notification

Title

Notification After Verification

Control

Providers MUST notify all necessary parties within 5 business days after completing the verification, assessment, and/or validation of transformative changes, also including the following information:
- Updates to all previously sent information
- Summary of any new risks identified and/or vulnerabilities resulting from the change (if applicable)
- Copy of the security assessment report (if applicable)