SI-13(03) Manual Transfer Between Components

NIST SP 800-53 (controls) 5.1.1+u4
All changes in this version
first version loaded SI part of SI-13

Title

Manual Transfer Between Components

Control

Manually initiate transfers between active and standby system components when the use of the active component reaches [Assignment: percentage] of the mean time to failure.

Discussion

For example, if the MTTF for a system component is 100 days and the MTTF percentage defined by the organization is 90 percent, the manual transfer would occur after 90 days.

Parameters

si-13.03_odp: percentage

Assessment objective

SI-13(03) transfers are initiated manually between active and standby system components when the use of the active component reaches [Assignment: percentage] of the mean time to failure.

STIG rules that implement this control 0