SR-05(01) Adequate Supply

NIST SP 800-53 (controls) 5.1.1+u4
All changes in this version
first version loaded SR part of SR-5

Title

Adequate Supply

Control

Employ the following controls to ensure an adequate supply of [Assignment: critical system components]: [Assignment: controls].

Discussion

Adversaries can attempt to impede organizational operations by disrupting the supply of critical system components or corrupting supplier operations. Organizations may track systems and component mean time to failure to mitigate the loss of temporary or permanent system function. Controls to ensure that adequate supplies of critical system components include the use of multiple suppliers throughout the supply chain for the identified critical components, stockpiling spare components to ensure operation during mission-critical times, and the identification of functionally identical or similar components that may be used, if necessary.

Parameters

sr-05.01_odp.01: controls
sr-05.01_odp.02: critical system components

Related controls

ra-9

Assessment objective

SR-05(01) [Assignment: controls] are employed to ensure an adequate supply of [Assignment: critical system components].

STIG rules that implement this control 0

No followed STIG rule cites a CCI indexed to this control (CCI list 2026-07-14).